ebc IT Governance Commitments
 PO: Planning and Organization Performance Target...[To top of Page]
Control Objective
& Performance Target
Service VariationsAcknowledgment
within
..
To Be Actioned By..Target Completion
within
..
Permissable % Variance
PO01 - IT Strategic Planning Snr Mgmt request...CBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
System AssessmentStandard2 daysSnr Mgmt Request30 days 
PO02 - IT Architectural Services Ron Huxter - 416-326-9440
PO03 - IT Plan Budget cycle...CBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
Operational PlanStandard Annual deadlinespecified dateChris Renaud 416-326-1660
PO04 - IT Organizational ReviewSnr Mgmt request...CBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
Org. Achievement ReviewStandard2 daysSnr Mgmt Request30 days 
Quality Assurance ReviewStandard2 daysSnr Mgmt Request30 days 
IT Security ReviewStandard2 daysSnr Mgmt Request30 days 
PO05 - IT Budget ReviewTrudy Hall - 416-326-4469
PO06 - IT MarketingCBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
PO07 - Personnel ManagementTrudy Hall - 416-326-4469
PO08 - External RequirementsPMO/Kevin Griffin - 416-327-8022
Requirements AssessmentStandard2 daysSnr Mgmt Request30 days 
PO09 - Risk Management.. John Lorenc - 416-212-2839
Threat-Risk or Vulnerability 2 daysSnr Mgmt Request30 days 
PO10 - Project ManagementPMO/Kevin Griffin - 416-327-8022
CBS Sharon Harvey - 416-326-9437
EDT/ENE Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
AS Ray Nakano - 416-326-9417
Service Standards  Upon Request10 days20%
Cost estimationStandard2 daysSnr Mgmt Request10 days20%
Complex2 daysSnr Mgmt Request20 days50%
Project DeliveryAll deliverables met On project end 10%
Projects Completed on time on project end 10%
Projects Completed within budget on project end 10%
PO11 - Quality Management.. PMO/AS/ITS unspecified
Customer SatisfactionOverall rating Annually80% rating20%
Snr client feedback Annually  
Technology Desk rating 1 out of 15 Incident Tickets3.5 out of 5 rating 
 AI: Acquisition and Implementation Performance Target...[To top of Page]
Control Objective
& Performance Target
Service VariationsAcknowledgment
within
..
To Be Actioned By..Target Completion
within
..
Permissable % Variance
AI01 - Automated Solution IdentificationCBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
AS Ray Nakano - 416-326-9417
 Requirements Definition
Basic5 daysBSM, AS, ITS30 days5%
AI02 - Application Software Acquisition and Maintenance Ray Nakano - 416-326-9417
 Software Build and Test
Basic5 daysAS Project MgrsPer Project Charter10%
AI03 - Technical Infrastructure Acquisition & Maintenance.. Ron Brittain - 416-326-7131
 Workstation ProvisionBasic STD PC1 dayService Request8 days5%
Accelerated STD PC1 dayService Request5 days5%
Additional approved SW1 dayService Request5 days5%
Additional non-approved SW1 dayService Request7 days5%
 Employee SetupBasic1 dayService Request2 days5%
 Network AccessBasic1 dayCompleted NARF5 days5%
 E-Mail AccessBasic1 dayService Request2 days2%
 Password ResetsDomain logon20 secService Request1 hr5%
App logon20 secService Request2 hrs5%
Network Move/Add/Change
1 to 5 jacks2 daysService Request5 days5%
6 to 10 jacks10 days
11 to 16 jacks15 days
17+ jacks8 wks or as arranged
Onsite visit2 daysMAC
Acknowledgement
5 days5%
Activation or De-activation
Basic2 daysService Request5 days5%
WS Configuration Change
SW only change2 daysService Request2 days5%
Part(s) In-Stock2 days
Parts Need to be Ordered15 days
WS Re-Image
PC Operational2 daysService Request2 days5%
Machine Failure5 days5%
 Mobile Services RAS-VPN Dial-in2 daysService Request and User dial-in number5 days2%
VPN High Speed2 daysService Request and existing ISPDSL: 7 days, Cable: 17 days5%
Hand-held
In-Stock
1 dayService Request and existing wireless provider2 days5%
Hand-held
Out-of-Stock
1 dayService Request and existing wireless provider15 days5%
AI04 - Technology Procedures Documentation and Maintenance..Brian Speed - 416-326-9480
ITSM website
HTML static page Mgmt Approval for posting15 days5%
AI05 - System Implementation and Accreditation..Ray Nakano - 416-326-9417
 User Acceptance Testing
Limited Test1 dayCAB Approval2 days5%
Regression Test1 dayCAB Approval20 days10%
New System Test1 dayPer Release Plan30 days10%
 Release Management
Standard1 dayCAB Approval20 days10%
 HW / SW Rollout
Standard1 dayebc CAB Approval60 days10%
AI06 - Change Management..Dean Johnson - 416-326-9472
 Change Approval
Standard2 daysRFC8 days5%
Emergency Sev 1 Incident1 day20%
 Server Re-configurationSimple2 daysCAB approvalchange window5%
Complexchange window5%
 Firewall MAC
Cluster Managed2 daysRFC to ebcCorporate CAB12 days5%
EDS/iSERV/DMZ Managed17 days
Emergency15 minEmergency Change approvalASAP2%
 IP Address Changes
ebc-hosted servers2 daysRFC to ebcCorporate CAB5 days5%
iSERV-hosted servers15 days
 Equipment RefreshBasic30 days of lease expirationPer Project CharterPer Project plan5%
New app/web/db serveriSERV-hosted2 daysRFC to CAB16 weeks2%
Voice processing modificationsPremium2 days TBDTBD
ACD Software ChangesPremium2 days TBDTBD
 DS: Delivery and Support Performance Target...[To top of Page]
Control Objective
& Performance Target
Service VariationsAcknowledgment
within
..
To Be Actioned By..Target Completion
within
..
Permissable % Variance
DS01 - Service Level Management..CBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
SLA Maintenance
Basic2 months priorSpecific date60 days5%
DS02 - Contract ManagementArch - Ron Huxter - 416-326-9440
ITS - Ron Brittain - 416-326-7131
AS - Ray Nakano - 416-326-9417
BM - Trudy Hall - 416-326-4469
PMO - Kevin Griffin - 416-327-8022
HW Lease Management
Basic1 dayPurchase Order14 days5%
DS03 - Availability/Capacity Management.. Robert Martin - 416-326-7132
Ray Nakano - 416-326-9417
Application Servers
Basic Availability Reporting98% uptime2%
Web Site AvailabilityBusiness Hours Monthly Reporting99.9% uptime.1%
Non-business Hours Monthly Reporting99.0% uptime1%
E-Mail AvailabilityBusiness Hours Monthly Reporting99.9% uptime.1%
Non-business Hours Monthly Reporting99.0% uptime1%
Network Availability24x7x365 Monthly Reporting98.5% uptime1.5%
Internet GatewayBusiness Hours Monthly Reporting99.0% uptime1%
Non-business Hours Monthly Reporting98.0% uptime2%
Server RestorationPer Incident Severity Incident ReportingPer Incident severity under DS10 - Incident/Problem Mgmt
DS04 - Service Continuity Management.. Ron Brittain - 416-326-7131
Ray Nakano - 416-326-9417
DS05 - IT Security Management.. John Lorenc - 416-212-2839
Logon/Application ID/PW IssuanceBasic1 dayCompleted NARF form5 days5%
Premium1 daySpecial Request1 day5%
PKI Certificate ModificationPremium1 dayService Request10 days5%
Security Advisory IssuanceBasicsame dayMgmt Authorizationsame day5%
CPIC Security ClearancePremium2 daysMgmt Authorization5 days5%
OPP Full Background CheckPremium2 daysMgmt Authorization90 days5%
DS06 - Cost ManagementCIO, Heads, BSMs
DS07 - Client Education and Training.. CBS Sharon Harvey - 416-326-9437
EDT/ENERGY Joan Berry - 416-326-7133
MOL Brian Miki - 416-212-0595
DS08 - Advise and Assist Clients Mara Goba - 416-326-7945
 Technology Service DeskBasic20 secTech Service Desk phone call< 15 min75%
 Referral to CTI GroupBasic20 secCreation of Incident Ticket30 min5%
DS09 - Configuration Management Robert Martin - 416-326-7132
Configuration Management
Basic  48 hrs5%
DS10 - Incident and Problem Management.. Incident: Mara Goba - 416-326-7945
Problem: Dean Johnson - 416-326-9472
IT Service FailureSeverity 120 secPer Severity Protocols8 hrs5%
Severity 220 sec60 minutes48 hrs5%
Severity 320 sec8 hrs5 days10%
Deskside SupportBasic20 sec 8 hrs25%
Premium Onsite within 4 hrs4 hrs10%
Premium Onsite visit1.5 hrs10%
Server Configuration FixEmergency15 minOnsite visit4 hrs20%
File RestorationSimple online, non-emailsame day 2 days5%
Complex offline, non-emailsame day 10 days5%
Email <7 dayssame day 2 days5%
Email >7 days2 days 5 days5%
Network Restoration
Basic15 mintriage8 hrs5%
EDS Level 2 Premium30 mintriage4 hrs2%
EDS Level 3 Premium30 mintriage2 hrs2%
Performance InvestigationBasic triage per Severity protocol10 days10%
Voice and ACD FailureBasic2 hrstriageper severity protocol10%
Problem ManagementBasic Mgmt request10 days10%
DS11 - Data Management Ray Nakano - 416-326-9417
Backup Management
ebc-hosted database serversdaily verificationset timeovernight5%
ebc-hosted file serversdaily verificationset timeovernight5%
DS12 - Facilities Management.. Robert Martin - 416-326-7132
DS13 - Operations Management.. Robert Martin - 416-326-7132
 M: Monitoring Performance Target...[To top of Page]
Control Objective
& Performance Target
Service VariationsAcknowledgment
within
..
To Be Actioned By..Target Completion
within
..
Permissable % Variance
M01 - Process Monitoring Brian Speed - 416-326-9480