1. Description

Hardware acquisition, standardizing on software, assessment of hardware and software performance, and consistent system administration. Many of these activities introduce minor changes to the infrastructure which are typically defined as "standard changes"; a change to the infrastructure which follows an established path, is relatively common, and is the accepted solution to a specific requirement or set of requirements. The factors defining a standard Change are: Once the approach has been established and documented, a standard Change process should be developed and promulgated to ensure that such Changes are efficiently processed to support the organization's business needs.

[To top of Page]

2. Service Activities

New HW and SW Assessment: assess new hardware and software for any impact on the performance of the overall system
HW and SW Acquisition, Move and Changes: Acquisition or modification of computer hardware and/or software (including providing, upon request, access to standard set of technology resources used within the Cluster) for use in business operations including issuance of Requests for Proposal/Resources, Purchase Order requisition, delivery and set-up, equipment removal or change, or
HW preventative maintenance: routine and periodic hardware maintenance to reduce the frequency and impact of performance failures. System software set-up including testing before use in the production environment is authorized.


[To top of Page]

3. Key Goal Indicators


ebc Service Commitments
  • develop Cluster standards for applications, and retire existing products/services as appropriate. Appropriate scope to workflow, correspondence management, document management, Web content management, management, travel expense claim processing and case management.
  • formal review/evaluation of new products for EBC use, in area of operational excellence and efficiency, concluding in business case and go/no go decision and implementation as appropriate,
  • analytical review of EBC's NT platforms, an assessment of the EBC positioning re MS support to the operating system, a risk assessment, costs analysis and strategy for moving ahead in 04-05,
  • Implement e-Forms for EBC business operations including identification of potential use with business benefit, business case, development and implementation,


[To top of Page]

4. Key Performance Indicators



ebc Service Commitments
Toolset Provisioning
    Workstation Provisioning
  • Upon receipt of an authorized Purchase Order, ebc will acknowledge that it is arranging the provisioning within 1 day and arrange for a standard desktop or laptop to be delivered complete with a standard image of all ebc standard software within 14 days 98% of the time.
  • For premium service the above delivery will be guaranteed within 5 days, 95% of the time,
  • Additional, approved software (not part of standard offering) will be installed in 5 days, 95% of the time while non-approved software will be installed in 7 days, 95% of the time.

    Access to Electronic Resources - including intra/internet Access

  • upon receipt of an authorized (signed by proper authority) network access requests will be acknowledged within 1 day and completed within 5 days in 95% of all requests,

    Electronic Mail

  • a request for an e-mail account will be acknowledged within 1 day of submitting a request through the Service Desk and an Outlook mail account will be established and included in the Government's Global Address List (GAL) within 2 days for 98% of all requests,

    Client Technology Assistance

  • requests for assistance with software or hardware will be acknowledged within 20 seconds of making a call to the ebc Service Desk, 85% of all requests will be resolved or referred to technical resources for resolution within 15 minutes
Network Moves, Adds and Changes (MACs)
    LAN Jack MACs
  • requests for a MAC of a LAN jack will be acknowledged within 2 days and a technician will be onsite within 5 days,
  • the time to complete the job will depend upon its' complexity. Guarantees are offered within the following volume bundles 95% of the time
    # Jacks to Be installedDays to Complete
    1 to 55
    6 to 1010
    11 to 1615
    > 1740
    or To be arranged
  • a request to activate or de-activate an existing jack will be acknowledged within 2 days with a technician onsite within 5 days to complete the job within 5 days. This will occur 95% of the time.

Workstation Re-image
  • A request to re-image a workstation will be acknowledged within 2 days.
  • for basic service a technician will appear onsite within 5 days and complete the re-imaging within 5 days
  • for business units with premium service service arrangements a technician will appear onsite within 2 days and complete the re-imaging within 2 days
  • the above two commitments will be met in 95% of all requests

Mobile Services
  • A request for remote dial-up over a VPN connection will be acknowledged within 2 days and upon providing the dial-in number. The request will be completed within 5 days, 98% of the time.
  • a request for a high-speed connection using VPN over Digital Subscriber Line (DSL) or cable will be acknowledged within 2 days. The requester must have an existing connection.
  • A DSL request will be completed within 7 days while cable will require 17 days to complete
  • The completion guarantees will be met 95% of the time.
  • A request for wireless access (Blackberry, iPAQ or other hand-held) will be acknowledged within 1 day. The requester will complete a woreless provider request form. The service will be completed within 15 days, 95% of the time.

Modify Workstation Configuration
  • An "In-stock" modification (one where non-standard items being configured on the machine are held in-stock by the supplier and do not require ordering) will be acknowledged within 2 days of receipt of an authorized Service Request (authorized implies correct approval for purchase of items). The request will be completed within 7 business days, 95% of the time.
  • An "Order-required" modification (one where non-standard items being configured on the machine are not held in-stock by the supplier and require special ordering) will be acknowledged within 2 days of receipt of an authorized Service Request (authorized implies correct approval for purchase of items). The request will be completed within 15 business days, 95% of the time.
[To top of Page]

5. Critical Success Factors



[To top of Page]

6. Additional Information

Maturity Level Characteristics






0 1 2 3 4 5

[To top of Page]